The question: what needs reordering, and by when? The report form of the replenishment workflow (§5.6): every product-and-warehouse pair whose projected quantity has reached its reorder point, with the suggested quantity — rounded up to the product's order multiple, never below its minimum order — the need date (today plus the lead time), the default supplier, and the supplier's actual recent lead times beside their promise. Under Planning the worklist is information to act on by hand; under Advanced it is also the launch pad for draft orders (§5.6). Rows you dismiss with a reason leave the list for the days you set — the worklist respects a decision once it is told.
User Manual · Chapter 5 — Inventory
The Replenishment worklist
Snapshot: portal-v0-2026-11-10